SUMMARY OF COMMON SENSE ADJUSTMENTS

TO THE ORANGE MODIFIED ROUTE

Suggested Adjustments

Cost Savings

Added Costs

Reduction in Property Impact

Refuge Acreage Required

1.
Campbell Point Reroute

$2,775,000

2.
High Bluff Reroute

$749,000

3.
Trail to Toe of Bluff

$184,000

4.
Eliminate Boardwalk

$650,000

2 Residential

5.
Trail to Toe of Bluff

$39,000

6.
Campbell Creek Reroute

$485,000

0.4 Acres
7.
Res. Point Tunnel Reroute

$144,000

1 Residential
0.1 Acres
8.
Bayshore Tunnel Reroute

$1,109,000

21 Residential
0.1 Acres
9.
Inland to Coastal trail

$565,000

10.
Eliminate Boardwalk

$1,161,000

16 Residential
1.0 Acres
11.
Move off private property

$2,084,000

15 Residential
0.5 Acres
12.
Shore Drive Tunnel Reroute

$317,000

6 Residential
0.4 Acres
13.
John's Park Reroute

$840,000

14.
John's Park Tunnel/Bd. Wk.

$2,083,000

11 Residential
3.5 Acres
15.
Move off private property

$2,212,000

31 Residential

16.
Railroad Reroute

$4,104,000

48 Jarvi Drive Homes nearby
3.0 &emdash; 4.0 Acres
17.
Potter Marsh No-Build

$3,984,000

TOTALS

$16 - $18 Million

$4.3 Million

103 Residential

9.0-10.0 Acres

The wildlife refuge contains over 32,000 total acres. The trail reroutes shown above require less than 10 of these acres along the edge of the refuge to be effective.

Eliminating the 97 residential property impacts shown above leaves less than 25 residential properties with impacts from the trail. The remainder of the impacted properties consist of large commercial tracts below the bluff or other land that has limited utility to the owners.